Apply for New LESCO Connection Online – Step by Step Guide (2025)

If you’ve recently built a new house, shop, or office in Lahore, you’ll need a new LESCO connection. Thankfully, the process is now digital and transparent, saving you long trips to LESCO offices.

In this guide, we’ll explain:

  • Who can apply for a LESCO new connection
  • Required documents
  • Step-by-step application process (online & offline)
  • Fees & processing time
  • How to track your application

Anyone who owns or rents a property (residential, commercial, or industrial) in LESCO’s jurisdiction can apply.

Eligible categories:

  • Residential users (homes, apartments, portions)
  • Commercial users (shops, plazas, small businesses)
  • Industrial consumers (factories, workshops)
  • Agricultural tube wells

LESCO New Connection Portal homepage.

Before applying, prepare scanned copies of the following documents:

DocumentPurposeNotes
CNIC copyApplicant’s identificationMust be valid and clear
Proof of ownershipProperty papers, registry, allotment letterIf rented, attach tenancy agreement
Undertaking /AffidavitStatement of no illegal connectionDownloadable from LESCCO site
Neighbors’ electricity bill copyFor location verificationOptional but recommended
Wiring Test Report (WTI)Certificate from licensed electricianFor load >1 kW
Two passport-size photosApplicant’s IDSoft copies accepted

Follow these steps to apply for a new LESCO connection online:

Step 1: Visit ENC (Electricity New Connection) Portal

Go to the official ENC Portal (used by all DISCOs including LESCO).

Step 2: Fill Out the Application Form

Provide details such as:

  • Applicant’s name, CNIC, father’s name
  • Property address & nearest consumer number (neighbor’s bill)
  • Connection type (domestic, commercial, industrial)
  • Load requirement (kW)

Step 3: Upload Required Documents

Attach scanned copies of CNIC, property papers, affidavit, etc.

Step 4: Submit Application & Print Tracking ID

After submission, you’ll get an Application Tracking ID. Save and print it.

Step 5: Verification & Site Inspection

  • LESCO staff will verify your documents.
  • A team may visit your site for inspection of wiring & load requirement.

Step 6: Pay Security Fee

You’ll receive a demand notice (via portal or office). This includes:

  • Security deposit (refundable)
  • Service connection charges

Pay at any bank branch, Easypaisa, or JazzCash.

Step 7: Meter Installation

After payment, LESCO schedules meter installation at your property. Timeline: Usually 30–45 days from application submission.

Charges depend on load, category, and type of connection.

CategorySecurity Deposit (PKR)Service Charges (PKR)Approx. Total (PKR)
Residential (1 Phase)4,000-6,0002,000-4,0006,000-10,000
Commercial (3 Phase)10,000-20,0005,000-10,00015,000-30,000
IndustrialVaries (based on load)High Chargescase-by-case

Note: Fees are NEPRA-approved and may change annually.

LESCO follows NEPRA’s service timelines:

Load RequirementProcessing Time
Up to 15 kW (Residential/Commercial)30 days
16–70 kW (Small Industry)45 days
Above 70 kW (Large Industry)60-90 days

Delays may occur if documents are incomplete or fees are unpaid.

You can check your LESCO new connection status using:

  1. ENC Portal: Enter tracking ID.
  2. LESCO Helpline 118: Call with CNIC or ID.
  3. LESCO Office: Visit nearest office with your tracking slip.

If you prefer visiting an office:

  1. Collect application form from LESCO Customer Service Center.
  2. Fill & attach required documents.
  3. Submit to office → get tracking ID.
  4. Pay security deposit & service charges at bank.
  5. Wait for inspection + meter installation.
  • Double-check all documents before submission.
  • Ensure wiring is tested & certified by licensed electrician.
  • Pay fees promptly after demand notice.
  • Track status regularly to avoid delays.

Applying for a LESCO new connection in 2025 is easier than ever thanks to the ENC online portal. With the right documents and timely fee payments, you can get your meter installed in 30–45 days.

Pro Tip: Always use the official ENC Portal or billlescoonline.pk for secure application tracking.

Q1. How long does it take to get a new LESCO connection?

Usually 30 days for domestic users, but industrial connections may take longer.

Q2. Can I apply for a LESCO new connection online?

Yes. Use the official ENC Portal to submit your application digitally.

Q3. What are the main charges for a new connection?

Security deposit + service connection charges, depending on load and category.

Q4. Can tenants apply for a new connection?

Yes, but they must provide a tenancy agreement + owner’s NOC.

Q5. How can I track my application status?

Enter your tracking ID on the ENC portal, or call LESCO helpline 118.